Projects - India

Our Indian Projects
Ocean India Hostel
Seeds India Hostel Complex
Single Storey Roof Villa
CLT Apparel India Pvt. Ltd.
BAI Unit-2
Staging Unit-3
Boiler Building

Staging Unit-4
Double Storey Villa
Adhishtan Villa Double Storey -05
Adhishtan Swimming Pool
Brandix Apparel Unit-III Expansion Project
Ocean India Finished Greigh Fabric ware house Floor Concrete
BAI Unit-II AHU Wash Room expansion work
Adhishtan Residential Apartment- Ongoing


Balance Works of Adhisthan Hostel Complex-Ocean.
Balance Construction Works in residential hostel building With Executive and Non Executive rooms 26 + 2 No’s Facility Rooms for ocean India with Internal and External Services like kitchen, chef room, parking of total built-up area of 32.5 Thousand sft. Including finishing and facilities, Landscaping etc.
Client : Adhisthan Investments
Value of Project : 13,495,170
Commencement Date : 20.Dec.2010
Completion Date : 05.May.2011
Days to Complete : 136 Days
Work done value : 11,962,781


















Ocean Boundary Wall
Construction of Parapet wall Length Of 220 Rmt With Fabricated Entry Door For Entire Ocean Hostel Complex.
Client : Adhisthan Investments
Value of Project : 567,700 (Inr)
Commencement Date : 21.Jan.2012
Completion Date : 13.Feb.2012
Days to Complete : 23 Days
Work done value : 567,700 (Inr)


















Seeds Hostel Complex, Executive, Non Executive & Ladies Hostel
Construction of Executive 16 Rooms & Non Executive 14 Rooms and Ladies 20 Rooms residential Hostel building Complex for Seeds With Internal and External Services, total built-up area of 95.8 Thousand sft. Including finishing and facilities, Road & landscaping etc.
Client : Adhisthan Investments
Value of Project : 54,985,492 (Inr)
Commencement Date : 01.July.2011
Completion Date : 01.April.2012
Days to Complete : 274 Days
Work done value : 42,979,245 (Inr)


















Clt Apparel India , Factory Building
Construction of Factory & Facility Building for Clt Apparel India with internal & External Facilities Like Water & Toilets& Canteen Building , Road , Drainage System ,Waste Water& Rain Water Disposal.
Client : CLT Apparel India Pvt.Ltd.
Value of Project : 68,965,268
Commencement Date : 03.May.2012
Completion Date : 09.Fed.2013
Days to Complete : 285 Days
Work done value : 58,993,065 (Inr)

















BAI - 2
Construction of Factory Facilities & Plant Operation RCC & PEB Building Like Generator Room And Chiller and Cooling Tower With Executive Staff Toilets With Internal & External Sewer & Plumbing Line With Rain Water Disposal.
Client: Brandix India Apparel India Pvt.Ltd.
Value of Projects: 29.78 Million
Commencement Date :-1St April 2013
Completion Date: - 1St July 2013
Days to Complete: 3 Months

















Staging Unit-3
Construction of Facility building at Plot no.08 (Staging Unit-III) with internal & external facilities like water & Toilets, Canteen building, Road, Rain water disposal and Waste water disposal
Client: Brandix India Apparel India Pvt.Ltd.
Value of Projects: 1,50,29,000 (INR)
Commencement Date :14 Dec 2012
Completion Date: - 14 May 2013


















Boiler Building
Construction of Boiler Foundation, Fule Handling, Toilets for Ocean India Factory building with Road work.
Client: Ocean India
Value of Projects: 87,00,000 (INR)
Commencement Date :19 Sep 2013
Completion Date: - 20 Feb 2014


















STG-4
Construction of Facility building at Plot no. 08/C (Staging unit-IV) with internal & external facilities like water & Toilets, Canteen Building, Road, Rain Water disposal and waste water disposal.
Client: Brandix India Apparel India Pvt.Ltd.
Value of Projects: 1,58,60,000 (INR)
Commencement Date “ 19th Sept 2013
Completion Date: - 20th Feb 2014
Days to Complete: 5 Months

















Double Storey Villa
Construction of Executive residential building Villa-Double Storey with internal and External services like car parking and lone, including finishing and facilities, landscaping etc.
Client: Adhishtan Investments India Pvt.Ltd
Value of Project: 3.79 Million
Commencement Date: “ 10th Oct 2013
Completion Date: - 10th Feb 2014
Days to Complete: 4 Months


















BAI-3
Construction of factory & facility building for BAI -3 with Internal & External Facilities Like Water & Toilets& Canteen Building Road, Rain Water Disposal , Waste Water Disposal.
Client: BAI Unit-03
Value of Project: 69.98 Million
Commencement Date “ 11 th November 2013
Completion Date: - 30 th April 2014
Project Status: On Going.

STG-4
Construction of factory & facility at  plot 8/C, ( Staging Unit-4) with Internal & External Facilities Like Water & Toilets& Canteen Building Road, Rain Water Disposal , Waste Water Disposal.
Client: Brandix India Apparel India Pvt.Ltd.
Value of Projects: 15.86 Million
Commencement Date “ 19 th Sept 2013
Completion Date: - 20 th Feb 2014
Days to Complete: 5 Months

 

Double Storey Villa
Construction of factory & facility at  plot 8/C, ( Staging Unit-4) with Internal & External Facilities Like Water & Toilets& Canteen Building Road, Rain Water Disposal , Waste Water Disposal.
Client: Brandix India Apparel India Pvt.Ltd.
Value of Projects: 15.86 Million
Commencement Date “ 19 th Sept 2013
Completion Date: - 20 th Feb 2014
Days to Complete: 5 Months


Construction of Executive Residential Building–Villa-1
Construction of Executive residential building –Villa-1 with Internal and External Services like car parking & lone of total built-up area of 2.5Thousand sft. Including finishing and facilities, landscaping etc.
Client :- Adhisthan Investments
Value of Project :- 15,35,233 (Inr)
Commencement Date :- 01.July.2011
Completion Date :- 15.Nov.2011
Days to Complete :- 150 Days
Work done value :- Includes in Seeds Hostel Complex.


















Executive Residential Building–Villa-2&3
Construction of Executive residential building –Villa-2&3 with Internal and External Services like car parking & lone of total built-up area of 5Thousand sft. Including finishing and facilities, landscaping etc.
Client : Adhisthan Investments
Value of Project : 3,689,886 (Inr)
Commencement Date : 01.March.2012
Completion Date : 15.July.2012
Days to Complete : 137 Days
Work done value : 3,607,557 (Inr)


















Adhistan Villa Double Storey
Construction of Executive residential building Villa-Double Storey with internal and External services like car parking and lone, including finishing and facilities, landscaping etc.
Client: Adhishtan Investments India Pvt.Ltd
Value of Project: 3.79 Million
Commencement Date: “ 10th Oct 2013
Completion Date: - 10th Feb 2014

















BAI-3 Factory & Facility Building
Construction of Factory and Facility building for BAI-3 with internal and external facilities like Water, Toilets, Road, Canteen Building. Rain water disposal and Waster Water disposal
Client: Brandix India Apparel City Pvt.Ltd - Unit-3
Value of Project: 6,99,80,000(INR)
Commencement Date: “ 01 nov 2013
Completion Date: - 30th april 2014

















Adhisthan Simming Pool
Supply of Materials and execultion of civil works of construct swimming pool In Non Processing Area(NPZ), complete and handover as per the drawings & specifications.
Client: Adhisthan Investments India pvt.Ltd
Value of Project: 12,593,177(INR)
Commencement Date: “ 29 oct 2015
Completion Date: - 28 feb 2016

















BAI-3 Factory & Facility Building Expansion Project
Supply of Materials and execution of civil works to construct, Complete and handover the expansion of factory & ancillary building with roads.
Client: Brandix Apparel India Pvt Ltd Unit-3
Value of Project: 34,921,219(INR)
Commencement Date: “ 11 Dec 2015
Completion Date: - 30 April 2016

















Ocean India Finished & GReigh Fabric Ware House Floor Concrete
Construcrtion of Ocean India Finished fabric ware House & Greigh fabric ware house Floor Concrete with VDF works.
Client: OCEAN INDIA Pvt Ltd
Value of Project: 36,60,276(INR)
Commencement Date: “ 19th Nov 2015
Completion Date: - 31st Jan 2016

















Adhishtan Residential Apartment Project
Supply of Material and execution of civil works to construct Service Apartment in NPZ, complete and handover as per the drawings & Specifications
Client: Adhishtan Investments India Pvt. Ltd
Value of Project: 52502233(INR)
Commencement Date: “ 10.06.2016
Completion Date: - 31.05.2017




























BIAC Staging Unit-05
Supply of Material and execution of civil works to construct Staging Unit-05 (Factory & Facility Building) in Plot no.C, BIAC SEZ, complete and handover as per the drawings & Specifications
Client: Brandix India Apparel City Pvt. Ltd
Value of Project: 16893136(INR)
Commencement Date: “ 19.10.2016
Completion Date: - 30.04.2017

















Tee Jay India Admin Office Building
Ongoing

Tee Jay Road Works
Ongoing

BIAC Staging Unit-06
Ongoing

Adhishtan Residential Apartment-2
Ongoing